Pre-Feasibility Study 2026 · Water Security Blueprint

25 CMS Bulk Treated Domestic Water Supply for Bulacan Province and Metro Manila

Metro Manila draws about 98% of its potable water from a single reservoir system. This study develops 25 cubic metres per second of new treated water from the Pampanga River at Apalit and conveys it 46 kilometres along the NLEX corridor — 20 CMS to Balintawak and 5 CMS to Bulacan Province — closing the whole of the 2030 deficit at an indicative bulk tariff of PHP 24.00 per cubic metre.

Pre-Feasibility Study · ATRCC-FS-2026-01, Rev. 0 · Issued 2026

Jump to dashboard
25 CMS
2,160 MLD of new treated water
46 km
NLEX corridor, Line A and Line B
PHP 40 bn
Estimated project cost
17.68%
Project internal rate of return
Water Storage and Advanced Treatment Plant Complex, 25 CMS · Apalit, Pampanga River · indicative site arrangement — click the image to enlarge

Chapter 1

Executive Summary

A single-source metropolitan supply operating at its dependable margin, and a run-of-river scheme that closes the near-term deficit without a new dam.

The problem

Metro Manila is a megacity of more than eighteen million people supplied from one reservoir. Approximately 98% of its potable water originates in the Angat-Ipo-La Mesa system. Dependable supply is 5,000 to 5,500 million litres per day, while requirement today is 5,400 to 5,700 million litres per day, so the system is already operating at or beyond its dependable margin and is held together by favourable hydrology, non-revenue water recovery and operational discipline. Demand grows at 2 to 3% each year. The published deficit is 700 to 1,200 million litres per day by 2030 and 2,000 to 2,500 million litres per day by 2040. Angat also serves irrigation and hydropower, which means every dry season forces an allocation contest between farms, faucets and the grid.

The proposition

The project develops 25 cubic metres per second of new water from the Pampanga River at Apalit, treats it to potable standard, and conveys it along a single 46-kilometre corridor following the North Luzon Expressway. Two distinct and separately metered pipelines run the full length of the corridor: Line A on the left side of the expressway serving Metro Manila, and Line B on the right side serving Bulacan Province. Each line comprises two 3,000-millimetre welded steel pipes designed at a Hazen-Williams C-factor of 140, a design capacity of 12,500 litres per second per pipe, a friction gradient of 0.3974 metres per 1,000 metres and a total dynamic head of 50 metres. Twenty cubic metres per second is delivered through Line A to the Balintawak Cloverleaf, where it enters the Metro Manila distribution system at a point served by both concessionaires, and five cubic metres per second is delivered through Line B to Bulacan Province through metered offtakes along the corridor, for a total system flow of 25 cubic metres per second.

The mechanism matters. The project does not require a new dam, a new watershed impoundment or a new reservoir permit at Angat. It develops an under-developed run-of-river resource and conveys it along an existing expressway corridor. That is why it can be delivered inside a construction window measured in years rather than the fifteen taken by comparable augmentation schemes.

Objective, service area and beneficiaries

Project Objective

Develop, treat and convey 25 CMS (2,160 MLD, 788.4 million cubic metres a year) of bulk treated domestic water from an under-developed run-of-river source, without a new dam or a new impoundment at Angat.

Service Area

Metro Manila via the Balintawak Cloverleaf, a delivery point served by both concessionaires, and Bulacan Province via two metered corridor connection points, CP-1 on the left line and CP-2 on the right line of the NLEX alignment.

Beneficiaries

More than eighteen million residents of Metro Manila served by the two concessionaires, plus the Bulacan provincial government and the concerned water districts receiving 5 CMS in two 2.5 CMS phases.

Summary of principal findings

Table 5 — principal findings of the study.

DimensionFinding
NeedConfirmed. The project closes the whole of the 2030 deficit and 86 to 108% of the 2040 deficit band.
Capacity25 CMS, equal to 2,160 MLD. Over three times the initial output of Wawa and comparable to the expected contribution of Kaliwa.
Technical feasibilityConfirmed. Standard welded steel transmission technology at verified design parameters, with no first-of-a-kind element.
Recommended configurationTwo distinct metered pipelines — Line A conveying 20 CMS to Balintawak for Metro Manila and Line B conveying 5 CMS to the Bulacan offtakes — each as 3,000 mm steel pipes × 2 over the full 46 km NLEX corridor, rather than each line sized for the full 25 CMS as submitted.
Estimated project costPHP 40 billion including contingencies and financing charges, equal to PHP 14.8 million per MLD of installed capacity.
Annual operating costPHP 9.7 billion at full output, equal to PHP 13.01 per cubic metre produced.
Energy intensity0.225 kWh per cubic metre, or 169 GWh per year, which is low because the scheme lifts water against a total dynamic head of only 50 m.
Indicative bulk tariffPHP 24.00 per cubic metre for domestic bulk supply at the 2031 price level, escalating at 3.5% per year.
Financial returnProject IRR of 17.68% against a WACC of 7.24%, on debt priced at 7.5% per annum repriced every five years across a 35-year term. Equity IRR of 26.92%. Minimum debt service coverage ratio of 3.17.
Economic returnEIRR of 39.4% and a benefit-cost ratio of 3.22 at a 10% social discount rate.
Public support requiredGovernment delivery of land and of the right-of-way along the NLEX corridor at a one-time cost of PHP 3.8 billion, with no viability gap funding and no recurring right-of-way charge required at the PHP 40.0 billion capital envelope.
Environmental classificationEnvironmentally critical project requiring a full Environmental Impact Statement and an Environmental Compliance Certificate from the DENR Environmental Management Bureau.
ScheduleFinancial close in 2028, construction from 2028 to 2031, commissioning and the output ramp in 2031, and full 25 CMS from 2032.
Principal riskRight-of-way acquisition along the 46-kilometre NLEX corridor carrying both pipelines, at a one-time cost of PHP 3.8 billion. It is the critical path and the single most probable cause of delay.

Data

Dashboard & Data Visualisations

Indicative planning-level figures drawn from the study: the supply-demand case, system output, capital and operating cost, tariff sensitivity to public support, and the output ramp.

Water demand projection, 2025 to 2066

Metro Manila reference demand band against dependable supply with and without the project. Without the project supply plateaus near 5,500 MLD; with the project it steps to approximately 7,660 MLD from 2031.

Production capacity allocation

Allocation of the 25 CMS system output: 20 CMS to Metro Manila via Balintawak, 5 CMS to Bulacan Province in two phases.

Delivered output by point, MLD

System total output of 2,160 MLD split between the metropolitan delivery point and the two Bulacan phases.

CAPEX breakdown, PHP million

Components of the PHP 40 billion capital envelope, including contingency, EPC, contractor profit and overhead, and indirect cost.

Required tariff against public support

Required domestic bulk tariff at alternative levels of viability gap funding. The recommended structure carries no viability gap funding.

Timeline and milestones — output ramp

Financial close in 2028, construction from 2028 to 2031, commissioning and partial output in 2031, and full 25 CMS from 2032.

PHP 9.7 bn

Annual operating cost at full output

PHP 13.01 / m³

Unit operating cost

0.225 kWh / m³

Energy intensity

169 GWh

Annual energy consumption

PHP 14.8 M / MLD

Capital intensity

788.4 M m³

Annual production at full output

YearDemand (MLD range)Basis
20255,400 to 5,700Reference situationer
20306,200 to 6,500Reference situationer
20407,500 to 8,000Reference situationer
20508,600 to 9,300Extrapolated at moderating growth
20669,600 to 10,400Extrapolated at moderating growth

Chapter 6

Technical Overview

Standard steel transmission technology with no first-of-a-kind element: river intake, full potable treatment, high-lift pumping at 50 m TDH, and two distinct metered pipelines of 3,000 mm steel pipes × 2 over a 46-kilometre expressway corridor.

Intake works

River intake on the Pampanga River at Apalit sized for the 25 CMS abstraction, with coarse and fine screening, sediment management and provision for low dry-season stage operation.

Low-lift pumping

Raw water pumping from the intake to the treatment complex, staged to follow river stage and treatment demand with standby units on each duty.

Treatment complex

Full potable treatment train — coagulation and flocculation, clarification, filtration and disinfection — with reverse osmosis membranes held as contingent scope for raw water quality excursions.

High-lift pumping

Treated water pumping into the two metered pipelines at a design total dynamic head of 50 m, with 13 duty pumps and 2 standby pumps rated 2,000 HP each, every unit passing 2,000 litres per second, together delivering the full 25 CMS system flow across Line A and Line B.

Conveyance mains

Two distinct metered pipelines over the full 46 km corridor — Line A on the left of the expressway serving Metro Manila with 20 CMS, and Line B on the right serving Bulacan with 5 CMS — each built as 3,000 mm welded steel pipes × 2 at a C-factor of 140, 12,500 LPS per pipe and a friction gradient of 0.3974 m per 1,000 m.

Materials and corrosion protection

Welded steel transmission mains with internal lining and external coating, cathodic protection, and corridor-specific crossings for waterways, roads and utilities.

Bulacan offtake works

Two separately metered connection points, CP-1 on the left line and CP-2 on the right line, each able to accept the full 5 CMS provincial allocation so each water district connects on the side nearest its storage.

Balintawak terminal reservoir

Terminal storage and metering at the Balintawak Cloverleaf, delivering 20 CMS into the metropolitan distribution system at a point served by both concessionaires.

Power supply and electrical works

Dedicated supply to the intake, treatment complex and pump stations with standby generation, medium-voltage distribution and SCADA across the corridor.

Design basis

ItemValueNote
Nominal capacity25 CMS2,160 MLD; 788.4 million m³ per year
SourcePampanga River at ApalitRun-of-river abstraction, no new dam
Corridor length46 kmAlong the North Luzon Expressway
Pipelines3,000 mm steel × 2 per lineLine A Metro Manila 20 CMS, Line B Bulacan 5 CMS
Hazen-Williams C140Adopted for both lines
Design flow per pipe12,500 LPSFriction gradient 0.3974 m per 1,000 m
Design TDH50 mBoth lines
Pumping13 + 2 standby × 2,000 HP2,000 LPS per pump
Metro Manila delivery20 CMSBalintawak Cloverleaf terminal reservoir
Bulacan delivery5 CMSCP-1 and CP-2 metered corridor offtakes
Right-of-way costPHP 3.8 bnOne-time; no recurring corridor charge
Debt pricing7.5% per annumRepriced every 5 years over a 35-year term
Franchise horizon2031 to 2066Matches the demand extension period

Chapter 7

Hydraulic Profile & Verification

Verification of the hydraulic basis confirms the engineering parameters for both metered pipelines — 46 km per line, 3,000 mm steel pipes × 2, C-factor 140, 12,500 LPS per pipe, a friction gradient of 0.3974 m per 1,000 m and 50 m total dynamic head — and a conveyance configuration that keeps full redundancy on the metropolitan duty while releasing cost.

Finding 1

Finding one — design parameters verified

The hydraulic basis is confirmed as stated. Each of the two pipelines runs 46 kilometres as 3,000 millimetre welded steel pipes × 2, at a Hazen-Williams C-factor of 140 and a design flow of 12,500 litres per second per pipe, giving a friction gradient of 0.3974 metres per 1,000 metres and a total dynamic head of 50 metres on both Line A and Line B. Pumping is provided by 13 duty units and 2 standby units rated 2,000 HP each, every unit passing 2,000 litres per second, consistent with the 50 metre head and with the 25 cubic metres per second total system flow. These parameters are adopted throughout this study and supersede any earlier variant heads.

Finding 2

Finding two — two distinct metered pipelines

Line A and Line B as originally submitted were each sized for the full 25 CMS, providing 50 CMS of transmission for a 25 CMS supply. This study adopts two distinct and separately metered pipelines over the full 46 km corridor at the verified parameters, with Line A carrying 20 CMS to Balintawak for Metro Manila and Line B carrying 5 CMS to the Bulacan offtakes with capacity held in reserve. The configuration retains full redundancy on the critical metropolitan duty while releasing approximately PHP 4,737 million of cost relative to the as-submitted arrangement, which is treated here as a high-redundancy variant costing PHP 36.7 billion.

Indicative residual head along the corridor

Design total dynamic head of 50 m on both Line A and Line B, dissipating at 0.3974 m per 1,000 m over the 46 km NLEX alignment from Apalit to Balintawak.

Corridor schematic

3,000 mm steel pipes × 2 per line at 12,500 LPS per pipe; Bulacan offtakes at CP-1 and CP-2.

0 km · Apalit intake46 km · BalintawakIntake &treatmentTerminalreservoirLine A · Metro Manila · 20 CMS · 3,000 mm × 2Line B · Bulacan · 5 CMS · 3,000 mm × 2CP-1CP-2Bulacan metered offtakes, 2.5 CMS each phase

Verified engineering design parameters

ParameterValueNote
Corridor length per line46 kmApalit intake to Balintawak, along NLEX
Pipes per line3,000 mm steel × 2Welded steel, lined and coated
Hazen-Williams C-factor140Adopted for both lines
Design flow per pipe12,500 LPSHydraulic design capacity
Friction gradient0.3974 m / 1,000 mAt C 140 and 12,500 LPS
Total dynamic head50 mLine A and Line B alike
Pump flow2,000 LPS per pumpUniform unit selection
Pump installation13 duty + 2 standby2,000 HP each
Line A delivery20 CMSMetro Manila at Balintawak Cloverleaf
Line B delivery5 CMSBulacan via CP-1 and CP-2 metered offtakes
Total system flow25 CMS2,160 MLD of treated water

Chapter 13

Financial statements and 35-year ledger

A PHP 40 billion capital envelope, 70% senior debt priced at 7.5% per annum repriced every five years over a 35-year term and 30% sponsor equity, supporting an indicative bulk tariff of PHP 24.00 per cubic metre with no viability gap funding required. The complete Chapter 13 and Annex C package is set out below — financial highlights, capital investment, loan schedule, income statement, cash flow, balance sheet, payback period and the year-by-year ledger. Indicative planning-level figures, in PHP billion unless noted.

17.68%
Project IRRvs. WACC 7.24%
26.92%
Equity IRR36-year operating horizon
PHP 72.40 bn
NPV at WACCpositive
7.24%
WACCnominal, post-tax
3.17
Minimum DSCRcovenant from 2032
PHP 24.00
Tariff per m³no subsidy required

Statement in view

Financial Highlights

Water allocation and project investment structure

Financial HighlightsWater allocation and project investment structure
ReferenceParticularsLPSCMDMLDCMS
1Treated bulk domestic water for Metro Manila20,0001,728,0001,72820
2Treated bulk domestic water for Bulacan Province5,000432,0004325
TotalFirm bulk capacity delivered at Balintawak and the Bulacan offtakes25,0002,160,0002,16025

Swipe the table sideways to see all columns.

Project Investment Cost

Debt and equity structure, PHP billion

Project Investment CostDebt and equity structure, PHP billion
ReferenceParticularsLoan (70%)Equity (30%)Total
1Loan 1 — CAPEX₱ 28.00₱ 12.00₱ 40.00
Total project investment cost₱ 40.00

Swipe the table sideways to see all columns.

Required domestic bulk tariff at alternative levels of public support

Table 6 — tariff sensitivity to viability gap funding.

Viability gap fundingGrant amountPrivately financed capitalRequired tariff, PHP per m³
0%PHP 0 billionPHP 40.0 billion22.00
15%PHP 4.8 billionPHP 27.2 billion20.81
35%PHP 11.2 billionPHP 20.8 billion19.22
50%PHP 16.0 billionPHP 16.0 billion18.04

Affordability is assessed against the alternatives rather than against the historical cost of Angat water. Seawater desalination is typically quoted between PHP 70 and PHP 110 per cubic metre in the Philippine context; the government support package required here is land, right-of-way, resettlement and watershed funding of PHP 3.8 billion as a single one-time cost, with no recurring right-of-way charge and no viability gap funding. Debt is priced at 7.5% per annum, repriced every five years across a 35-year term.

Basis of estimate

Estimated project cost is PHP 40 billion. Of that, PHP 19,532 million is direct construction cost, PHP 977 million is contingency at 5%, PHP 1,641 million is EPC cost, PHP 3,076 million is contractor's profit and overhead, and PHP 6,774 million is indirect cost, including PHP 3,864 million of disturbance compensation to NLEX for in-and-out mobilisation, traffic, security and hazard assistance, and provision for the construction period, temporary storage, staging and warehousing. The three largest packages — the treatment complex and the two pipelines — account for close to four fifths of direct cost, 79%. Right-of-way and land along the 46-kilometre corridor are carried at a single one-time cost of PHP 3.8 billion, delivered through the government support package; the financial model carries no recurring annual right-of-way charge for the pipelines.

Revenue and tariff

The required tariff is a direct function of how much of the capital cost the private party must recover from water sales, and of the cost of the debt that funds it. Debt is priced at 7.5% per annum, repriced every five years across a 35-year term, and the capital envelope of PHP 40 billion is fully privately financed while the PHP 3.8 billion right-of-way and land cost sits with government. On that basis the tariff required to deliver the target return is PHP 24.00 per cubic metre and no viability gap funding is required. That figure sits well below seawater desalination, typically quoted between PHP 70 and PHP 110 per cubic metre in the Philippine context, and above the older and much smaller Wawa scheme. It is the price of new water at scale from an undeveloped basin, and it should be assessed against the alternatives rather than against the historical cost of Angat water, which reflects infrastructure built and paid for decades ago.

Chapters 10 to 12

Environmental & Social Impact

An environmentally critical project requiring a full Environmental Impact Statement and an Environmental Compliance Certificate, with corridor safeguards, monitoring and a phased engagement programme.

Classification and required instrument

The scheme is an environmentally critical project. It requires a full Environmental Impact Statement and an Environmental Compliance Certificate issued by the DENR Environmental Management Bureau, with scoping accepted immediately under the Water Security Blueprint priority-processing arrangement.

Impact identification

Principal impacts are river abstraction and downstream flow, construction disturbance along the 46 km expressway corridor, spoil and sludge management at the treatment complex, noise, air quality and traffic during construction, and permanent land take at the intake, plant and terminal reservoir sites.

Environmental management and monitoring

An Environmental Management Plan covering abstraction limits and environmental flow, sludge handling, erosion and sediment control, and corridor reinstatement, supported by a monitoring programme with river gauging, water quality sampling and multipartite monitoring participation.

Water resource safeguards

A twelve-month river gauging and dependable-flow verification programme at the proposed intake is the single highest-value investigation for retiring project risk, with a dry-season operating strategy if one-in-twenty dry year flow proves insufficient.

Social safeguards and right-of-way

Easement rather than purchase along the corridor wherever possible, statutory valuation and disturbance compensation, livelihood restoration where access is affected, and a defined approach to the Balintawak constraint at the metropolitan delivery point.

Stakeholder engagement

A phased engagement programme with MWSS, the concessionaires, the Bulacan provincial government and water districts, NLEX, host local government units and affected communities, together with a grievance redress mechanism and a local benefit package.

Chapter 15

Implementation Schedule

Financial close in 2028, construction on multiple fronts to 2031, commissioning and output ramp in 2031, and full 25 CMS in service from 2032.

  1. 2026 to 2027

    Preparation and permitting

    Original proponent status, franchise negotiation, EIS scoping, water permit processing, corridor delineation and parcellary survey, and the twelve-month dependable-flow verification programme.

  2. 2028

    Financial close

    Government support package committed, take-or-pay offtake executed with a creditworthy counterparty, and construction mobilisation on multiple fronts.

  3. 2028 to 2030

    Construction

    Intake and low-lift works, treatment complex, and simultaneous conveyance fronts along the NLEX corridor with high-lift pump stations and the Balintawak terminal reservoir.

  4. 2031

    Commissioning and output ramp

    Line testing, disinfection and staged commissioning, with partial output delivered to Balintawak and the Bulacan Phase 1 offtake.

  5. 2032

    Full output

    Full 25 CMS in service — 20 CMS to Metro Manila and 5 CMS to Bulacan Province across CP-1 and CP-2.

  6. 2032 to 2066

    Operations and renewal

    Operation to defined performance standards, lifecycle renewal of mechanical and electrical assets, and long-term resilience under the disaster recovery and business continuity plan.

Critical path

The critical path runs through right-of-way acquisition along the 46-kilometre NLEX corridor carrying Line A and Line B. It is the single most probable cause of delay, and the schedule assumes the corridor can be secured within twenty-four months, funded from the PHP 3.8 billion right-of-way provision, with delineation and survey commencing in advance of financial close.

Chapters 1.7 and 1.8

Conclusion & Recommendations

The study reaches a favourable conclusion, conditional on four matters being settled. Eight recommendations follow for the approving authorities and the Proponent.

Recommendations

  1. 01

    Accord the Proponent original proponent status for the project and commence negotiation of the franchise agreement under the franchise framework.

  2. 02

    Direct the DENR Environmental Management Bureau to accept scoping for a full Environmental Impact Statement immediately, on the accelerated timetable, on the strength of the Water Security Blueprint priority-processing arrangement.

  3. 03

    Direct the National Water Resources Board to process the water permit application for 25 cubic metres per second from the Pampanga River, with a dependable-flow study as a condition precedent rather than a condition to filing.

  4. 04

    Authorise the DPWH and the concerned local government units to commence corridor delineation and parcellary survey for the 46-kilometre right-of-way in advance of financial close, funded from the PHP 3.8 billion right-of-way provision in the government support package.

  5. 05

    Commission a twelve-month river gauging and dependable-flow verification programme on the Pampanga River at the proposed intake, as the single highest-value investigation for retiring project risk.

  6. 06

    Require the Proponent to carry the verified engineering parameters — 46 km per line, 3,000 mm steel pipes × 2, C-factor 140, 12,500 LPS per pipe, 0.3974 m per 1,000 m, 50 m TDH and 13 + 2 standby pumps of 2,000 HP at 2,000 LPS each — into the detailed engineering design, and to submit an independent hydraulic model review.

  7. 07

    Approve the government support package comprising land, right-of-way, resettlement and watershed funding of PHP 3.8 billion as a single one-time cost, with no recurring right-of-way charge and no viability gap funding.

  8. 08

    Constitute the offtake arrangements early: a take-or-pay bulk water supply agreement with MWSS or under any innovative legal approach of contracted engagement for a new water source covering the 20 CMS metropolitan volume, and bulk water supply agreements with the Bulacan provincial government and the concerned water districts covering the 5 CMS provincial volume.

Conditions on which this conclusion depends

  • The Pampanga River can dependably yield 25 cubic metres per second at the intake in a one-in-twenty dry year, after respecting existing downstream entitlements and environmental flow.
  • The right-of-way along the 46-kilometre corridor can be secured within twenty-four months.
  • A take-or-pay offtake is executed with a creditworthy counterparty before financial close.
  • The public support package — land, right-of-way, resettlement and watershed funding of PHP 3.8 billion — is committed as a one-time cost.

If any of these four conditions fail, the project as structured does not proceed on the terms described, and the risk chapter sets out the fallback position for each.

Take the study with you

Download the full summary as an editable Word document, including every data table on this page.